{"id":4268,"date":"2022-08-03T08:34:00","date_gmt":"2022-08-03T08:34:00","guid":{"rendered":"https:\/\/www.willedonker.nl\/extra-work-in-construction-forewarned-is-forearmed\/"},"modified":"2025-07-29T11:53:33","modified_gmt":"2025-07-29T11:53:33","slug":"extra-work-in-construction-forewarned-is-forearmed","status":"publish","type":"post","link":"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/","title":{"rendered":"Extra work in construction. Forewarned is forearmed!"},"content":{"rendered":"\t\t<div data-elementor-type=\"wp-post\" data-elementor-id=\"4268\" class=\"elementor elementor-4268 elementor-2443\" data-elementor-post-type=\"post\">\n\t\t\t\t\t\t<section class=\"elementor-section elementor-top-section elementor-element elementor-element-1f10418 elementor-section-boxed elementor-section-height-default elementor-section-height-default\" data-id=\"1f10418\" data-element_type=\"section\" data-e-type=\"section\" data-settings=\"{&quot;jet_parallax_layout_list&quot;:[]}\">\n\t\t\t\t\t\t<div class=\"elementor-container elementor-column-gap-default\">\n\t\t\t\t\t<div class=\"elementor-column elementor-col-100 elementor-top-column elementor-element elementor-element-16993ca\" data-id=\"16993ca\" data-element_type=\"column\" data-e-type=\"column\">\n\t\t\t<div class=\"elementor-widget-wrap elementor-element-populated\">\n\t\t\t\t\t\t<div class=\"elementor-element elementor-element-2e5fbb0 elementor-widget elementor-widget-text-editor\" data-id=\"2e5fbb0\" data-element_type=\"widget\" data-e-type=\"widget\" data-widget_type=\"text-editor.default\">\n\t\t\t\t<div class=\"elementor-widget-container\">\n\t\t\t\t\t\t\t\t\t<h4>Alert duty<\/h4><p>Additional work means extra work for a contractor and therefore more costs. That makes sense. But the question is who pays for those costs. The contractor or the client? Under the law, the contractor has a duty to warn. He must inform the client in a timely manner that additional work will result in additional costs. If the duty to warn is fulfilled, the costs will be borne by the client. Forewarned is forearmed, so to speak.<\/p><p>But what exactly does this duty to warn entail? Should the contractor also provide advance insight into the exact cost of the extra work? Or can the contractor suffice with the mere notice that the additional work will result in a price increase? This regularly arises in practice. Judges ruled differently on this issue.<\/p><h4><strong>Supreme Court provides clarity<\/strong><\/h4><p>Recently, the Supreme Court (HR July 1, 2022, <a href=\"https:\/\/uitspraken.rechtspraak.nl\/inziendocument?id=ECLI:NL:HR:2022:989\" target=\"_blank\" rel=\"noopener\">ECLI:NL:HR:2022:989<\/a>) tied the knot. The outcome favors contractors. In short, the contractor does not have to submit the arithmetic to the client in advance by himself. It is sufficient for him simply to state that the additional work will result in a price increase. If the client wants to know exactly what it is going to cost, he should take the lead and have a conversation with the contractor about it.<\/p><h4><strong>Additional work  <\/strong><\/h4><p>Additional work is an addition or change in the agreed work desired by the client. When building a house, for example, one might think of additional dormer windows compared to the original design. Or, for example, the choice of a better or more luxurious material than originally envisioned. The law provides that in such a case, the contractor must promptly alert the client to the need for a resulting price increase, unless the client should have understood that need by itself.<\/p><h4><strong>The Supreme Court&#8217;s decision<\/strong><\/h4><p>The Supreme Court has clarified how the law should be interpreted on this point. The point is that the client knows in advance that the additional work desired will cost him money. Indeed, consent to additional work does not automatically also mean consent to a price increase, the Supreme Court said. If the client cannot himself suspect that the extra work is going to lead to extra, the contractor has a duty to warn. The client must be protected from financial surprises. However, this protection does not go so far as to also require the contractor to pre-calculate in advance to the client exactly what the additional work will cost. If the client does want to know, he should take the initiative and discuss this with the contractor.<\/p><h4>Price<\/h4><p>But what if, although the client was well informed, the price was not discussed with the contractor? In that case, a &#8220;reasonable price&#8221; is due for the additional work. In that case, the pricing should follow the prices that the contractor normally negotiates for similar work and what is common in the market.<\/p><h4>Practical<\/h4><p>The Supreme Court ruling favors contractors. It provides additional tools for collecting an overtime claim. At the same time, it still remains important to properly record arrangements for additional work in writing (e.g., by e-mail). This can be used to prove in retrospect that the client agreed to the additional work and knew it would result in a price increase. In turn, to avoid unpleasant surprises, the client would do well to seek clarification from the contractor in advance as to the exact extent of the price increase. Again, the advice is to put agreements in writing.<\/p><h4>Cost-increasing circumstances?<\/h4><p>In addition to additional work, a price increase may also be at issue in so-called cost-increasing circumstances. These are circumstances that come to light after the conclusion of the contract and cannot be attributed to the contractor. An extraordinary increase in commodity prices comes to mind. In that situation, the contractor is subject to a similar duty of warning as for additional work. Therefore, the Supreme Court ruling may also be relevant in cost-increasing circumstances. That would mean that even in that situation, the contractor does not have to state in his warning exactly how much the client will have to pay extra. Whether this parallel can be drawn will have to be seen in case law.<\/p><p>This contribution was written by <a href=\"https:\/\/www.willedonker.nl\/team\/mr-m-p-c-van-essen\/\" target=\"_blank\" rel=\"noopener\">Mr. Michiel van Essen<\/a>, affiliated with the <a href=\"https:\/\/www.willedonker.nl\/vakgebieden\/vastgoed\/\" target=\"_blank\" rel=\"noopener\">Real Estate Practice Group<\/a>.<\/p>\t\t\t\t\t\t\t\t<\/div>\n\t\t\t\t<\/div>\n\t\t\t\t\t<\/div>\n\t\t<\/div>\n\t\t\t\t\t<\/div>\n\t\t<\/section>\n\t\t\t\t<\/div>\n\t\t","protected":false},"excerpt":{"rendered":"<p>Alert duty Additional work means extra work for a contractor and therefore more costs. That makes sense. But the question is who pays for those costs. The contractor or the client? Under the law, the contractor has a duty to warn. He must inform the client in a timely manner that additional work will result [&hellip;]<\/p>\n","protected":false},"author":3,"featured_media":5353,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[81],"tags":[],"sectoren":[],"class_list":["post-4268","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-real-estate"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v27.5 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Extra work in construction. Forewarned is forearmed! - Wille Donker<\/title>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Extra work in construction. Forewarned is forearmed! - Wille Donker\" \/>\n<meta property=\"og:description\" content=\"Alert duty Additional work means extra work for a contractor and therefore more costs. That makes sense. But the question is who pays for those costs. The contractor or the client? Under the law, the contractor has a duty to warn. He must inform the client in a timely manner that additional work will result [&hellip;]\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/\" \/>\n<meta property=\"og:site_name\" content=\"Wille Donker\" \/>\n<meta property=\"article:published_time\" content=\"2022-08-03T08:34:00+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2025-07-29T11:53:33+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/www.willedonker.nl\/wp-content\/uploads\/2023\/09\/1-1.png\" \/>\n\t<meta property=\"og:image:width\" content=\"600\" \/>\n\t<meta property=\"og:image:height\" content=\"300\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"Timo\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Timo\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"4 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/nieuws\\\/extra-work-in-construction-forewarned-is-forearmed\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/nieuws\\\/extra-work-in-construction-forewarned-is-forearmed\\\/\"},\"author\":{\"name\":\"Timo\",\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/#\\\/schema\\\/person\\\/84284671e900322ec9b979fc9ae0c3b7\"},\"headline\":\"Extra work in construction. Forewarned is forearmed!\",\"datePublished\":\"2022-08-03T08:34:00+00:00\",\"dateModified\":\"2025-07-29T11:53:33+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/nieuws\\\/extra-work-in-construction-forewarned-is-forearmed\\\/\"},\"wordCount\":727,\"publisher\":{\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/nieuws\\\/extra-work-in-construction-forewarned-is-forearmed\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/www.willedonker.nl\\\/wp-content\\\/uploads\\\/2023\\\/09\\\/1-1.png\",\"articleSection\":[\"Real estate\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/nieuws\\\/extra-work-in-construction-forewarned-is-forearmed\\\/\",\"url\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/nieuws\\\/extra-work-in-construction-forewarned-is-forearmed\\\/\",\"name\":\"Extra work in construction. Forewarned is forearmed! - Wille Donker\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/nieuws\\\/extra-work-in-construction-forewarned-is-forearmed\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/nieuws\\\/extra-work-in-construction-forewarned-is-forearmed\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/www.willedonker.nl\\\/wp-content\\\/uploads\\\/2023\\\/09\\\/1-1.png\",\"datePublished\":\"2022-08-03T08:34:00+00:00\",\"dateModified\":\"2025-07-29T11:53:33+00:00\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/nieuws\\\/extra-work-in-construction-forewarned-is-forearmed\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/nieuws\\\/extra-work-in-construction-forewarned-is-forearmed\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/nieuws\\\/extra-work-in-construction-forewarned-is-forearmed\\\/#primaryimage\",\"url\":\"https:\\\/\\\/www.willedonker.nl\\\/wp-content\\\/uploads\\\/2023\\\/09\\\/1-1.png\",\"contentUrl\":\"https:\\\/\\\/www.willedonker.nl\\\/wp-content\\\/uploads\\\/2023\\\/09\\\/1-1.png\",\"width\":600,\"height\":300},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/nieuws\\\/extra-work-in-construction-forewarned-is-forearmed\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/home-2\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Extra work in construction. Forewarned is forearmed!\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/#website\",\"url\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/\",\"name\":\"Wille Donker\",\"description\":\"Divers, Realistisch &amp; Betrokken.\",\"publisher\":{\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/#organization\",\"name\":\"Wille Donker\",\"url\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/www.willedonker.nl\\\/wp-content\\\/uploads\\\/2022\\\/11\\\/logo-willedonkers-wit.svg\",\"contentUrl\":\"https:\\\/\\\/www.willedonker.nl\\\/wp-content\\\/uploads\\\/2022\\\/11\\\/logo-willedonkers-wit.svg\",\"caption\":\"Wille Donker\"},\"image\":{\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/#\\\/schema\\\/logo\\\/image\\\/\"}},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/#\\\/schema\\\/person\\\/84284671e900322ec9b979fc9ae0c3b7\",\"name\":\"Timo\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/6ce5cd5bcc3183574adf7677cbb8ff9798fd7620f3935986a279830a794bb1c8?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/6ce5cd5bcc3183574adf7677cbb8ff9798fd7620f3935986a279830a794bb1c8?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/6ce5cd5bcc3183574adf7677cbb8ff9798fd7620f3935986a279830a794bb1c8?s=96&d=mm&r=g\",\"caption\":\"Timo\"},\"url\":\"https:\\\/\\\/www.willedonker.nl\\\/en\\\/nieuws\\\/author\\\/timosera\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Extra work in construction. Forewarned is forearmed! - Wille Donker","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/","og_locale":"en_US","og_type":"article","og_title":"Extra work in construction. Forewarned is forearmed! - Wille Donker","og_description":"Alert duty Additional work means extra work for a contractor and therefore more costs. That makes sense. But the question is who pays for those costs. The contractor or the client? Under the law, the contractor has a duty to warn. He must inform the client in a timely manner that additional work will result [&hellip;]","og_url":"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/","og_site_name":"Wille Donker","article_published_time":"2022-08-03T08:34:00+00:00","article_modified_time":"2025-07-29T11:53:33+00:00","og_image":[{"width":600,"height":300,"url":"https:\/\/www.willedonker.nl\/wp-content\/uploads\/2023\/09\/1-1.png","type":"image\/png"}],"author":"Timo","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Timo","Est. reading time":"4 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/#article","isPartOf":{"@id":"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/"},"author":{"name":"Timo","@id":"https:\/\/www.willedonker.nl\/en\/#\/schema\/person\/84284671e900322ec9b979fc9ae0c3b7"},"headline":"Extra work in construction. Forewarned is forearmed!","datePublished":"2022-08-03T08:34:00+00:00","dateModified":"2025-07-29T11:53:33+00:00","mainEntityOfPage":{"@id":"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/"},"wordCount":727,"publisher":{"@id":"https:\/\/www.willedonker.nl\/en\/#organization"},"image":{"@id":"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/#primaryimage"},"thumbnailUrl":"https:\/\/www.willedonker.nl\/wp-content\/uploads\/2023\/09\/1-1.png","articleSection":["Real estate"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/","url":"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/","name":"Extra work in construction. Forewarned is forearmed! - Wille Donker","isPartOf":{"@id":"https:\/\/www.willedonker.nl\/en\/#website"},"primaryImageOfPage":{"@id":"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/#primaryimage"},"image":{"@id":"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/#primaryimage"},"thumbnailUrl":"https:\/\/www.willedonker.nl\/wp-content\/uploads\/2023\/09\/1-1.png","datePublished":"2022-08-03T08:34:00+00:00","dateModified":"2025-07-29T11:53:33+00:00","breadcrumb":{"@id":"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/#primaryimage","url":"https:\/\/www.willedonker.nl\/wp-content\/uploads\/2023\/09\/1-1.png","contentUrl":"https:\/\/www.willedonker.nl\/wp-content\/uploads\/2023\/09\/1-1.png","width":600,"height":300},{"@type":"BreadcrumbList","@id":"https:\/\/www.willedonker.nl\/en\/nieuws\/extra-work-in-construction-forewarned-is-forearmed\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.willedonker.nl\/en\/home-2\/"},{"@type":"ListItem","position":2,"name":"Extra work in construction. Forewarned is forearmed!"}]},{"@type":"WebSite","@id":"https:\/\/www.willedonker.nl\/en\/#website","url":"https:\/\/www.willedonker.nl\/en\/","name":"Wille Donker","description":"Divers, Realistisch &amp; Betrokken.","publisher":{"@id":"https:\/\/www.willedonker.nl\/en\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.willedonker.nl\/en\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/www.willedonker.nl\/en\/#organization","name":"Wille Donker","url":"https:\/\/www.willedonker.nl\/en\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.willedonker.nl\/en\/#\/schema\/logo\/image\/","url":"https:\/\/www.willedonker.nl\/wp-content\/uploads\/2022\/11\/logo-willedonkers-wit.svg","contentUrl":"https:\/\/www.willedonker.nl\/wp-content\/uploads\/2022\/11\/logo-willedonkers-wit.svg","caption":"Wille Donker"},"image":{"@id":"https:\/\/www.willedonker.nl\/en\/#\/schema\/logo\/image\/"}},{"@type":"Person","@id":"https:\/\/www.willedonker.nl\/en\/#\/schema\/person\/84284671e900322ec9b979fc9ae0c3b7","name":"Timo","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/secure.gravatar.com\/avatar\/6ce5cd5bcc3183574adf7677cbb8ff9798fd7620f3935986a279830a794bb1c8?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/6ce5cd5bcc3183574adf7677cbb8ff9798fd7620f3935986a279830a794bb1c8?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/6ce5cd5bcc3183574adf7677cbb8ff9798fd7620f3935986a279830a794bb1c8?s=96&d=mm&r=g","caption":"Timo"},"url":"https:\/\/www.willedonker.nl\/en\/nieuws\/author\/timosera\/"}]}},"_links":{"self":[{"href":"https:\/\/www.willedonker.nl\/en\/wp-json\/wp\/v2\/posts\/4268","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.willedonker.nl\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.willedonker.nl\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.willedonker.nl\/en\/wp-json\/wp\/v2\/users\/3"}],"replies":[{"embeddable":true,"href":"https:\/\/www.willedonker.nl\/en\/wp-json\/wp\/v2\/comments?post=4268"}],"version-history":[{"count":4,"href":"https:\/\/www.willedonker.nl\/en\/wp-json\/wp\/v2\/posts\/4268\/revisions"}],"predecessor-version":[{"id":9317,"href":"https:\/\/www.willedonker.nl\/en\/wp-json\/wp\/v2\/posts\/4268\/revisions\/9317"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.willedonker.nl\/en\/wp-json\/wp\/v2\/media\/5353"}],"wp:attachment":[{"href":"https:\/\/www.willedonker.nl\/en\/wp-json\/wp\/v2\/media?parent=4268"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.willedonker.nl\/en\/wp-json\/wp\/v2\/categories?post=4268"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.willedonker.nl\/en\/wp-json\/wp\/v2\/tags?post=4268"},{"taxonomy":"sectoren","embeddable":true,"href":"https:\/\/www.willedonker.nl\/en\/wp-json\/wp\/v2\/sectoren?post=4268"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}